| # Mega-Project Counter Tests |
| |
| The directory includes three tests for the counter mega-project example: |
| |
| 1) IO Ports Test: |
| |
| * Configures the user space lower 8 IO pins as outputs |
| * Observes the counter value through the configured pins in the testbench |
| |
| 2) Logic Analyzer Test 1: |
| |
| * Configures LA probes [31:0] as inputs to the management SoC to monitor the counter value |
| * Configures LA probes [63:32] as outputs from the management SoC to set the counter initial value |
| * Flags when counter value exceeds 500 through the management SoC gpio |
| * Outputs message to the UART when the test concludes successfuly |
| |
| 3) Logic Analyzer Test 2: |
| |
| * Configures LA probes [64] and [65] as outputs from the management SoC to set counter clock and reset values |
| * Provides counter clock and monitors the counter value after five clock cycles |